Maintenance of LC vertical long axis turbine pumps

Date:2022/9/16 21:49:55

Views:


Source:Vertical Turbine Pump Manufacturer and Vertical Suspension Pump Prices Provider

Maintenance of LC vertical long axis turbine pumps


LC type vertical long axis turbine pumps should be disassembled and repaired when necessary (vibration, noise, bearing temperature exceeding allowable value, flow rate, head significantly decreased, etc.). For continuous operation of vertical long axis turbine pumps, regular inspection should be carried out every year.

(1) Prepare spare parts in advance for the maintenance of vertical long-axis pumps.

(2) Disassemble the vertical long axis turbine pump according to the reverse assembly sequence. After disassembly, the rust spots on the parts should be removed and then re-painted.

(3)Check the clearance between the impeller and seal ring. Please refere to below chart.

Norminal diameter

125

160

200

250

315

400

500

630

The maximum clearance allowed

 

1.1~1.8

 

1.2~2.0

 

1.3~

2.2

 

1.5~

2.5

 

1.7~

2.8

 

1.9~

3.1

 

2.1~

3.5

 

2.4~

4.0

Check the abrasion of guide bearing. Please see below table for reference.

Nominal diameter

60

80

100

120

140

160

180

The maximum clearance allowed

 

0.4~0.8

 

0.5~0.9

 

0.6~1.0

 

0.7~1.2

 

0.8~1.3

 

0.9~1.4

 

1.0~1.5

4) Check the abrasion of the shaft sleeve and the packing sleeve. If the abrased slots diameter reaches 1~2mm, please replace it.

5) Check the abrasion of the impeller and impeller body.

6) Replace the sealing parts , like packing seal, O-ring seal and paper washer.

7) Assemble the pump in order and rotate the pump rotors which should run smoothly.

Attention:

The safety procedure and regulations should be followed throughout the inspection. Before any inspection, please do as below:

1.Cut the motor power off and all the instruments.

2.Shut the outlet and inlet valve.

3. Cut off cooling water.

Maintenance of LC vertical long axis turbine pumps